74488 REL 24: 1992-061-02 EXP ALBENI FALLS WILDLIFE MITIGATION - KALISPEL |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Matthew Berger | Kalispel Tribe | Yes | Technical Contact | mberger@knrd.org | (509) 447-7244 |
Thomas Delorenzo | Bonneville Power Administration | Yes | Env. Compliance Lead | tdelorenzo@bpa.gov | (503) 230-4419 |
Ray Entz | Kalispel Tribe | Yes | Supervisor | rentz@knrd.org | (509) 445-1147 |
Bart George | Kalispel Tribe | Yes | Contract Manager | bgeorge@kalispeltribe.com | (509) 671-6149 |
David Kaplowe | Bonneville Power Administration | Yes | F&W Approver | djkaplowe@bpa.gov | (503) 230-5365 |
Kendra Maroney | Kalispel Tribe | No | Technical Contact | kmaroney@kalispeltribe.com | (509) 671-2376 |
Jolene Seymour | Kalispel Tribe | No | Administrative Contact | jseymour@kalispeltribe.com | (509) 445-1147 |
Virgil Watts III | Bonneville Power Administration | Yes | COR | vlwatts@bpa.gov | (503) 230-4625 |
Elham Zolmajd-Haghighi | Bonneville Power Administration | Yes | Contracting Officer | ezolmajd-haghighi@bpa.gov | (503) 230-7414 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Completion of Required Project Reporting to BPA | B: 119. Oversight of New Projects, Implementation, Construction, O&M, RM&E w/ participating agencies | 02/28/2022 | 02/28/2022 | |
Completed documentation of environmental compliance to BPA | C: 165. Complete Permit Applications and Provide Documentation to Obtain Compliance. | 02/28/2022 | 02/28/2022 | |
Completed Coordination with all Tribal Departments & Leadership | D: 191. Internal Coordination | 02/28/2022 | 12/31/2021 | |
Completed Acquisition and Easement Agreements | E: 172. Pre-Acquisition work | 02/28/2022 | 02/28/2022 | |
Completed FY21 Annual Report to BPA | F: 132. Annual Report for 2021 Contract Cycle | 02/28/2022 | 02/28/2022 | |
Maintain Existing fences | G: 186. Fence Maintenance Idaho | 11/30/2021 | 11/30/2021 | |
Create and enhance Wetland Ponds and plug Agricultural drainage ditches. | H: 181. Create and enhance Wetland Ponds on Washington Management Area | 02/28/2022 | 12/30/2021 | |
Wetland Ponds and shorelines seeded and mulched | I: 47. Plant created wetland areas with trees and shrubs. | 10/30/2021 | 10/29/2021 | |
Properties Secured From Trespass | J: 26. Secure Properties and Provide Enforcement Management. | 02/28/2022 | 12/30/2021 | |
Maintained Access to Water Control Structures. | K: 38. Maintain Access to Water Control Structures. | 02/01/2022 | 09/30/2021 | |
Water Control Structures Maintained and Functioning | L: 186. Maintain Existing Water Control Structures and Replace Flow Control Culverts on Wetland Enhancement Sites. | 10/30/2021 | 10/30/2021 | |
Buildings and nursery maintained | M: 186. Maintain buildings | 02/28/2022 | 12/30/2021 | |
Vegetation Removal Idaho lands | N: 199. Removal Vegetation Idaho Mitigation Lands | 10/30/2021 | 10/30/2021 | |
Maintain planted vegetation in Washington. | O: 198. Maintain planted vegetation in Washington | 10/28/2021 | 10/28/2021 | |
Provide parking areas and kiosks for visitors. | P: 188. Provide parking and kiosks for visitors as needed | 02/28/2022 | ||
Maintenance of Vegetation on Idaho properties | Q: 198. Maintain planted vegetation in Idaho | 10/30/2021 | 09/30/2021 | |
Completed Fence Maintenance Washington Mitigation Properties | R: 186. Fence Maintenance Washington | 10/28/2021 | 09/30/2021 | |
Planted Riparian Areas on Enhancement Sites | S: 47. Plant Native Trees and Shrubs-WA management units. | 10/28/2021 | 09/30/2021 | |
Removal of Noxious Vegetation from Washington Mitigation Properties | T: 199. Remove Vegetation WA Mitigation Properties | 10/28/2021 | 10/28/2021 | |
Field Nursery maintenance | U: 198. Maintain field Nursery for plant materials | 11/30/2021 | 12/30/2021 | |
Land Management Plans | V: 193. Complete Management Plans for new and update existing plans. | 02/28/2022 |
Primary Focal Species | Work Statement Elements |
---|---|
Wildlife |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | |||||||
B | 119 | Oversight of New Projects, Implementation, Construction, O&M, RM&E w/ participating agencies | |||||||
C | 165 | Complete Permit Applications and Provide Documentation to Obtain Compliance. | |||||||
D | 191 | Internal Coordination | |||||||
E | 172 | Pre-Acquisition work | |||||||
F | 132 | Annual Report for 2021 Contract Cycle | |||||||
G | 186 | Fence Maintenance Idaho | 06/08/2021 | ||||||
H | 181 | Create and enhance Wetland Ponds on Washington Management Area | 06/08/2021 | ||||||
I | 47 | Plant created wetland areas with trees and shrubs. | 06/08/2021 | ||||||
J | 26 | Secure Properties and Provide Enforcement Management. | |||||||
K | 38 | Maintain Access to Water Control Structures. | 06/08/2021 | ||||||
L | 186 | Maintain Existing Water Control Structures and Replace Flow Control Culverts on Wetland Enhancement Sites. | 06/08/2021 | ||||||
M | 186 | Maintain buildings | 06/08/2021 | ||||||
N | 199 | Removal Vegetation Idaho Mitigation Lands | 06/08/2021 | ||||||
O | 198 | Maintain planted vegetation in Washington | 06/08/2021 | ||||||
P | 188 | Provide parking and kiosks for visitors as needed | 06/08/2021 | ||||||
Q | 198 | Maintain planted vegetation in Idaho | 06/08/2021 | ||||||
R | 186 | Fence Maintenance Washington | 06/08/2021 | ||||||
S | 47 | Plant Native Trees and Shrubs-WA management units. | 06/08/2021 | ||||||
T | 199 | Remove Vegetation WA Mitigation Properties | 06/08/2021 | ||||||
U | 198 | Maintain field Nursery for plant materials | 06/08/2021 | ||||||
V | 193 | Complete Management Plans for new and update existing plans. |